This is an annual program to clean and evaluate the existing conditions of the sanitary sewer system throughout the city. Approximately one-fifth of the city will be cleaned each year, which means the entire city will be cleaned and televised every five years. This program is designed to safe-guard private property and public health while ensuring that sanitary sewer service remains uninterrupted.
During the cleaning of the sewer, you may hear the air rushing through your homes venting system; this is normal. In the rear case that your homes venting system is not properly functioning, some water may be discharged through the water fixtures or drain.
If you smell sewer gases, pour diluted bleach down your trapped drains as the cleaning action may have removed water from the traps. If after pouring water down all of your drains the gas smell does not go away, call Engineering at 675-8251.
This is an annual program to replace damaged streets and sidewalks. The City of Trenton does not replace driveway approaches unless the damage to the approach was caused by the city utilities or city related work. All concrete is inventoried on a yearly basis to determine areas needing replacement. Paint marks on the concrete indicate areas to be replaced. If there is concrete marked in front of your driveway, you may not be able to access your drive for seven days once the concrete has been removed. If this is the case, the contractor will deliver a notice letting you know when this concrete will be replaced.
Dominic Gaglio Construction ((734) 281-7453) was awarded the 2009 Concrete Replacement Contract.
The 2009 Concrete Program will continue for the season in May, 2010. The program will continue again in the spring with the contractor replacing pavement throughout the city on an as needed basis, focusing north of West Road and west of Fort Street.
The City of Trenton is pleased to announce that D&D Water & Sewer, Inc. (7371 Haverhill Lane, Canton, MI 48187, (734) 397-3386) has been contracted to construct the Trumbull Avenue Water Main Replacement Project (Emeline to Trumbull Court). Construction of the project will start Monday, April 19, 2010. There shall be no parking on the street during construction. The contractor will begin the project by installing the main line and then after testing is completed, the individual water services will be removed and replaced (additional notice will be given when any water is to be shut off during construction). During the project you may experience low water pressure and/or rusty water. This is NOT an unsafe condition and is expected at times. If your water becomes rusty, run your cold water faucet in the basement or lower level of your house until the water runs clear. Do not run your hot water or do laundry until your water runs clear. The project will be completed this year. If you have any questions or concerns, please contact the Engineering Department at 675-8251.
This project has been completed and the new water main is in service. Minor restoration and final punchlist items will be addressed starting the week of April 12, 2010. If you have any questions or concerns regarding this project, please contact the Engineering Department at 675-8251.
The City of Trenton is please to announce that Century Cement Company, Inc. (12600 Sibley Road, Riverview, MI 48193, (734) 284-8770) has been contracted to construct the Maple Street Reconstruction Project between West Jefferson and Third Street. Construction is scheduled to start Wednesday, May 5, 2010. Due to the proximity of this project to the Trenton Fire Station, the project will be completed in three phases. During construction, Maple Street will be closed from Third Street to West Jefferson. There will be no parking along Maple Street (West Jefferson to Third Street) during the project. If you have any questions or concerns, please contact the Engineering Department at (734) 675-8251.